Building contract claims

Building contract claims

Chappell, David

114,28 €(IVA inc.)

Many building projects are the subject of claims the assertion of a right, usually by the contractor, to an extension of the contract period or an additional payment under the terms of the building contract. Many of these claims are unsound or ill-founded, often because the basic principles are misunderstood. This highly regarded book examines the legal basis of claims for extensions oftime and additional payment, and what can and cannot be claimed under the main forms of contract. It includes chapters dealing with direct loss and expense, liquidated damages, extension of time, concurrency problems, acceleration, time at large, common law and contractual claims, global claims, and heads of claim and their substantiation. With the publication of the fifth edition, Building Contract Claims has been thoroughly revised to ensure it is fully up to date with the latest contracts, court judgments and building practice. Changes include: Coverage of over 60 additional relevant court cases Coverage of the 2005 JCT contracts suite Coverage of changes to the NEC contract Coverage of additional contracts such as Constructing Excellence; Measured Term Contract andthe ACA PPC2000 contract together with the 2005 relevant JCT sub-contracts Important changes to liquidated damages and to extensions of time, and the giving of notices Appendix 1 has been substantially revised Like its predecessors, the fifth edition of Building Contract Claims will be essential reading for architects, contract administrators, project managers and quantity surveyors, aswell as contractors, contracts consultants and construction lawyers. INDICE: Preface vii Acknowledgements x Contract abbreviations xi PART I 1 1 Introduction 3 1.1 Structure of the book 3 1.2 Types of claims 3 1.3 The basis of claims 8 1.4 Architect's and contract administrator's powers and liability to contractor 11 1.5 Quantity surveyors powers 16 2 Time 20 2.1 Time of theessence 20 2.2 Time at large 22 2.3 Extension of time clauses in contracts 262.4 Concurrency 32 2.5 Acceleration 40 2.6 Sectional completion 47 2.7 The SCL extension of time Protocol 51 3 Liquidated damages 57 3.1 The meaning and purpose of liquidated damages 57 3.2 Liquidated damages or penalty 58 3.3 Liquidated damages as limitation of liability 65 3.4 Sums greater than a genuine pre-estimate 66 3.5 Liquidated damages as an exhaustive remedy 67 3.6 Injunction 72 3.7 Liquidated damages in relation to loss 74 3.8 Where there is no breach of contract 75 3.9 Calculation of liquidated damages 77 3.10 Where there is partial possession 78 3.11 Maximum recovery if sum is a penalty 80 3.12 Maximum recovery if liquidated damages do not apply 82 3.13 Defences to liquidated damages in building contracts 84 3.14 Bonus clauses 93 4 Basis for common law claims 95 4.1 General 95 4.2 Implied terms 97 4.3 Variation of contract 103 4.4 Omission of work to give it to others 104 4.5 Extra work 107 4.6 Possession of site 109 4.7 Site conditions 113 5 Direct loss and/or expense 117 5.1 Defi nition 117 5.2 Direct v indirect 118 5.3 Exclusion of consequential loss 120 6 Points of principle 123 6.1 Measure of damages 123 6.2 Burden of proof 124 6.3 Res ipsa loquitur 125 6.4 Mitigation of loss 125 6.5 Betterment 127 6.6 Notices128 6.7 Categories of claim 135 7 Potential heads of claim 140 7.1 Foreshortened programme 140 7.2 The knock-on effect 143 7.3 The more common heads of loss 147 7.4 Cost of a claim 180 8 Causation 182 8.1 Theory 182 8.2 Use of networks 184 8.3 Float 189 9 Global claims 192 9.1 Basic principles of global claims192 9.2 Unacceptable global claims 194 9.3 The current position 196 10 Preparation and substantiation of claims 201 10.1 Preparing a claim 201 10.2 Types of evidence required to support a claim 206 10.3 Scott schedules 213 PART II 217 11 Extension of time under JCT standard form contracts 219 11.1 Standard Building Contract (SBC) 219 11.2 Intermediate Building Contract (IC and ICD) 248 11.3 Minor Works Building Contract (MW and MWD) 251 11.4 Design and Build Contract (DB) 254 11.5 Prime Cost Building Contract (PCC) 256 11.6 Management Building Contract (MC) 257 11.7 Construction Management Trade Contract (CM/TC) 25911.8 Major Project Construction Contract (MP) 260 11.9 Measured Term Contract(MTC) 262 11.10 Constructing Excellence Contract (CE) 264 12 Liquidated damages under JCT standard form contracts 268 12.1 Standard Building Contract (SBC)268 12.2 Intermediate Building Contract (IC and ICD) 273 12.3 Minor Works Building Contract (MW and MWD) 273 12.4 Design and Build Contract (DB) 274 12.5 Prime Cost Building Contract (PCC) 275 12.6 Ma

  • ISBN: 978-0-470-65738-6
  • Editorial: John Wiley & Sons
  • Encuadernacion: Cartoné
  • Páginas: 544
  • Fecha Publicación: 12/08/2011
  • Nº Volúmenes: 1
  • Idioma: Inglés